Selçuk Zeybek

Notes · Testing

Testing: who pays when it passes

Under Sub-Clause 7.4 the Engineer can order extra tests — and who pays turns on one thing: the result. If the extra test shows the work was good, it's a Variation the Employer wears, with time, cost and profit; if it shows a defect, the Contractor bears it. Shown through a railway rail-weld example.

Testing — Sub-Clause 7.4

Who pays when the test passes — FIDIC Yellow Book

aluminothermic weldultrasonic test — specified72h noticeto attendweld passescut out sampleadditional test — Clause 13FAILContractor paysPASSEmployer payslab: compliant ✓cut-out & re-weldlab feesplant standinglost possessiontime + cost + profitEngineer a no-show?deemed present —readings acceptedTest passes, the Employer pays. Test fails, you do.

The contract specifies the test — here, ultrasonic testing of a rail weld.

What Sub-Clause 7.4 actually covers

7.4 governs testing during the Works — of Materials, Plant and workmanship, as the job is built. It is deliberately distinct from the two later test gates in the Yellow Book: Tests on Completion under Clause 9 (before the Employer takes over) and Tests after Completion under Clause 12 (the performance tests once it is in use). Mixing them up is the classic error: 7.4 is the day-to-day testing that runs alongside construction — the concrete cubes, the rebar, the welds, the factory acceptance tests on the signalling.

The rule that catches people

The Engineer may, under Clause 13, vary a test or order additional tests. Who pays for that extra testing turns on a single fact — the result:

Extra test shows…Who paysBasis
Compliant (passes)The EmployerA Variation under Cl. 13 — plus 7.4 gives time, Cost and reasonable profit.
Defective (fails)The Contractor7.4 makes the Contractor bear the cost, notwithstanding any other provision.

Two mechanics sharpen it. The Engineer must be given not less than 72 hours’ notice to attend a test; if he does not, the Contractor may proceed and the test is deemed made in his presence, with his acceptance of the readings deemed. And the same profit-bearing entitlement in 7.4 catches an Employer-caused delay to testing — late free-issue, late attendance, late power for a dynamic test.

On a railway

Take the rail welds. The contract specifies ultrasonic testing of each aluminothermic weld — a 7.4 test. The welds pass. The Engineer, still uneasy, instructs the Contractor to cut out a sample of completed welds and send them for destructive laboratory break-testing — an additional test under Clause 13. The lab confirms every weld sound. Because the extra test proved the work compliant, the Employer wears the whole cost of that detour — cutting out and re-welding, the lab fees, the welding gang and plant standing idle, and the track possession lost — and, because it flows through 7.4, the Contractor recovers time, Cost and reasonable profit. Had a weld failed, the result flips entirely: the Contractor bears it, and the failed weld becomes a rejection and remedial-work question under 7.5 and 7.6.

A second common one: dynamic testing of the signalling and train detection needs the traction power energised. If the Employer is late energising the overhead line, the specified test cannot run — the test teams and possession stand idle. That is an Employer-caused delay to testing, and 7.4 carries it: extension of time, Cost, and reasonable profit.

← All notesGet in touch →